London's
big question was: What kind of bridge will allow carts &
horses to cross over it, AND tall ships to sail under it? Horace
Jones, the City Architect, had an answer: A bascule
bridge. (The word bascule comes from the French word
for "seesaw.")
His
bridge would raise its bascules to let the tall ships pass through,
and it had walkways, high above the ships' masts, where pedestrians
could cross as the ships passed underneath.
Sadly,
Horace Jones never saw Tower Bridge. He died in 1887 before the foundations
were complete. The famous engineer John Wolfe Barry, who had helped
Horace Jones with his bascule bridge design, oversaw the construction
of Tower Bridge.
How
can you build a bridge like that, with all that boat traffic on the
river?
You start with the foundation. And in the case of Tower Bridge,
you start deep, deep, deep under the surface of the Thames –
10 metres below the surface of the water, in fact.
Top of Page
Building
the Piers
Work began on 22nd April 1886. Divers prepared the riverbed for the
massive piers. It must have been a scarey job – after all, this
was 1886. They didn't have scuba gear and safety
devices and computer equipment. The divers wore leather suits with
metal helmets, and they were connected to the surface by air tubes.
They prepared the riverbed.
Above
them, on barges, other workers created caissons.
Caissons are open-ended watertight boxes, with sharp edges. Workers
lowered the caissons into the river – down, down, down –
until they rested on the riverbed. While the sharp edge of the caisson
dug into the riverbed, the workers forced them deep into the soil.
They were sunk to 9 metres deep, into watertight London clay. The
London clay would support the enormous weight of Tower Bridge!
Twenty-four
caissons were constructed (12 in each pier), and when they were complete,
they were filled with concrete. The workers left space within each
pier for steel pillars (which would support the towers), and for the
bascule machinery. It took four years to construct the piers!
Top
of Page
Building
the Towers
The
steel for the towers was made by William Arrol and Company in Scotland,
then shipped down to London and brought up the river on barges. There
wasn't much space to store equipment and materials, so the steel was
brought up the river when it was needed. Crews of workers set about
200 rivets per day – by hand. There are two million rivets in
Tower Bridge – so you can do the math.The work took a long time.
Slowly but surely, the steelwork rose from the Thames like a huge
black skeleton. Each tower had four steel pillars. The two pillars
on the land-side of the tower would support the suspension chains,
while the river-side pillars would support the high level walkways.
Top
of Page
Building
the Walkways
When
the pillars were finished, workers started building the high level
walkways. They worked 46 metres above the river, without safety nets!
Boats would pass below them, so they had to be extra careful not to
drop a tool onto someone's head. The workers on Tower Bridge
were paid an oustanding wage of £2 per week! It may
not seem like much, but it was twice the wage of a London policeman.
Separate crews worked on cantilevers extending from
each tower. (A cantilever is a section supported at one end, which
can bear its own weight.) When the cantilevers extended far enough
toward the middle, a central section linked them together.Good ole
William Arrol & Company in Scotland had tested their steel to
make sure it would all fit snugly together once it arrived at Tower
Bridge.
Top
of Page
Building
the Chains & the Bascules
The
suspension chains of Tower Bridge are really heavy. They weigh one
ton per foot! They needed to support all that weight, so the workers
built an abutment on each land-end of Tower Bridge.
(An abutment is a structure which anchors suspension chains.) Then
they built the suspension chains, using scaffolding to support them
as they went. When the chains were finished, the workers added rods
and girders to keep the chains from swinging in the wind.
The
bascules were next! Remember, these were the "arms"
of Tower Bridge which would raise and lower to let the ships pass
through. They built sections forty feet long, strengthened with long
girders and cross-girders. Then they built the counterbalance.
(The counterbalance is the part which balances the bascule, kind of
like a person on the seat of a seesaw. If you have only one person,
the seesaw can't move. The bascule itself had a weight, so it needed
a counterbalance in order to go up and down.) On the counterbalance,
they constructed a huge gear, which fit into the gear of the steam
engine. When the steam engine built up pressure, the gears would turn,
opening the bridge for ships! When it released pressure, the bascules
lowered.
With
its bascules, the suspension chains and the steam engine, Tower Bridge
was a triumph of engineering! Its nickname was "the Wonder
Bridge." After 8 years of hard work, Tower Bridge was
finally finished and ready for its grand opening.
On 30th June 1894, the Thames River was packed with barges, steamships
and ferries. People crowded along the embankments and bridges for
a peek at the new bridge. The Prince and Princess of Wales arrived
amidst the excitement. The Prince made an official declaration that
the bridge was open for traffic; then he pushed a button which raised
the bascules for the first time.